18kWp array completed!

Taking advantage of the good weather, we have completed the 18kWp array this afternoon. All connections double checked and output readings verified, so working well!

Tomorrow we'll be commisioning the inverters onto the buildings 3 phase power circuit and finalising tests and certification.

The whole array went in very smoothly onto the Kalzip roof. Although there were 4 times as many brackets to install than other roof mount systems, because no structural or drilling work was involved, together with usual waterproofing, this system has a sleek low profile design with no mess to clean up.